January 11th, 2012 | Author:

There will be a public meeting for information and public comment on Florida’s Early Restoration Projects Thursday, January 12 at the UWF Conference Center (1100 University Pkwy, Pensacola, FL 32514). Open house starts at 6 PM. Meeting and Comments session begins at 7 PM.

The meeting will give the state Department of Environmental Regulation (DEP) and federal agencies an indication of the importance to our community of marine restoration projects. This is a great opportunity to provide your support for reefing project funding in our area from the BP Oil Spill funds being allocated by the state of Florida.

July 29th, 2009 | Author:

A Gulf Side reef design change from straight concrete pilings to piling mounted eco system reefs
will result in lowering estimated cost from approximately $330,000 from $400K to $70K.

Attendees at the July 29th Marine Sanctuary Committee Meeting agreed that it was great change. Especially in light of the reported durability of the same reefs mounted along the Alabama coast line during recent storms. Reefs located in the surf zone there withstood recent storms better than some concrete pilings that snapped. They also provide more surface area and their discs can be adjusted in height after deployment if so desired. Escambia county was also impressed with the option and is changing the design of their gulf side reef planned for the Portofino area.

Speaking of permitting –

Target dates for the permit application package and submittal to the county for official application with FL DEP and US Army Corp of Engineers are as follows:

Package to Marine Sanctuary Committee – August 7th
Package published on website – August 14th
Public Comment Meeting – August 25th